THE AVENUE HOSPITAL EXTENSION 2021-04-01T09:39:12+11:00

THE AVENUE HOSPITAL EXTENSION
VICTORIA

Four levels, 36 modules: installed in just two days for the Avenue Hospital in Windsor.

Modscape was engaged by Ramsay Health Care to develop a modular solution that enabled them to quickly meet the hospital’s increasing accommodation demands while minimising disruption to patients, staff and visitors. Designed by Billard Leece Partnership Architects, the 36 modules, making up four levels, were installed in just two days. Erilyan carried out the site works for the project while the ‘cold shell’ was constructed off-site within Modscape’s Brooklyn factory.

The modules were delivered with a complete façade and structural system. Following installation, concrete floors were poured into each level over a two-week period.

The end modular solution was 1,500sqm of ‘cold shell’ building completed in three weeks on-site and ready for the fitout of operating theatres over the coming months.

Project specifications

  • 36 modules over four levels
  • 1,500sqm ‘cold shell’ modular health space ready for the fitout of operating theatres
  • Installed in two days